Integrated transport link Szczecin Łękno
Construction of an integrated transport link Łękno with infrastructure on the Srednicowa Route to serve passenger traffic within the agglomeration in Szczecin

Location: Szczecin (Poland)
Contracting entity: Szczecin City Council
Budget: PLN 137,794,344.66 (including VAT)
Completion year: 2021
Execution period: 34 months

Characteristics
The contract includes the construction of a new road on the section from Arkońska Street to Wojska Polskiego Avenue including sidewalks, bike lanes and new parking spaces and the construction of theękno system interchange track and tram system. Within the scope of the work, the following works stand out: construction of 5 viaducts, retaining walls, a level crossing, execution of networks (supply of rainwater, drinking water, telecommunications, electricity, gas), reconstruction of catenary, assembly of railway traffic control equipment, installation of acoustic screens, execution of urbanization and recreation elements.