Higher College of Technology New Campus

 Location: Baniyas, Abu Dhabi, UAE
 Developer: ADVETI
 Budget: 504,000,000 AED
 Completion year: 2021
 Execution period: 33 months

CHARACTERISTICS:
The works involves the Construction, Completion, Maintenance and handing over of the project.

The main actions are:
- Construction of Higher Colleges of Technology New Campus (G+2+R) total plot size area of 213,096.66 sqm
- Total Build-up area 100,573.40 sqm
- External Hard and Softscape Area of 159,605.26 sqm
- Education Buildings:

  • Male 41,327 sqm
  • Female Campus 40,319 sqm

- External Buildings (Auditorium, Sports Center, Headquarters, Service Blocks, Innovation Center, Electrical Substation, Central Kitchen) with 18,191 sqm
- Civil and Architectural Works
- Finishes
- External Works
- MEP Works