Bulk Cargo Terminal Infrastructure, Phase I.
Ploce (Croacia)
Location: Ploce (Croacia)
Developer: Port of Ploce Authority
Budget: 54.198.945 €
Execution period: 42 meses
CHARACTERISTICS:
Dredging works in access channel and basin up to -20.00 m. depth. Slope protection with riprap and geotextile, land reclamation and ground improvements with stone columns. Jetty construction with reinforced concrete deck slab of dimensions 400 x 35 m., founded over steel piles of diameter 1500 and 1000 mm. and 50 m. long, 30 m. embedded. Execution of 150,000 m2. in land surface.
- Removing preloads: 375.000 m3
- Dredging and fillings: 1.330.000 m3
- Soil improvement with stone columns: 173.000 m3
- Steel piles: 10.800 t.
- Concrete deck slab: 47.000 m3
- Steel reinforcement in deck slab: 4.830 t.
- Geotextiles and waterproofing in esplanades: 230.000 m2
- Base layers stabilized with cement: 110.000 m2
- Bituminous pavement : 25.430 m2
- Railroad track: 4.341 m