slide1

Berth for large vessels at the docks of Poniente

CHARACTERISTICS

Works consist in the extension of the Poniente docks in the Port of Palma de Mallorca to host the increased cruise demand in the island. The current quay will be enlarged 400 m long and 30 m width. The solution includes the provision of 18 reinforced concrete floating caissons placed individually to get a permeable wall enabling water regeneration inside the basin.
Pile mooring demolition         
– Trench dredge:  28.643 m3
– Rock bedding layer: 135.250 t.
Manufacturing and sinking 18 reinforced concrete floating caissons
Caissons dimensions:
– Length:  29,15 ml.
– Beam: 14,95 ml.
– Depth: 15,70 y 16,40 ml.
– Concrete: 33.275 m3
– Steel reinforcement: 2.827,115 Kg.
Filling cells
Capping beam execution
– “In situ” slabs casted using a floating structure formwork and hydraulic lifting equipment.
    * Concrete:   15.377 m3
    * Steel reinforcement: 2.827,115 Kg
Concrete ramp between the current quaid and the new extension:
Installations and pavement
Berthing and mooring elements
– 42 Bollards of 200 tons<br>
– 36 Fenders type SC2000H

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn