High Science Technology Superior Center
Location
Valencia, Spain
Contracting entity
Fundación Valenciana de Biomedicina. Generalitat Valenciana
Execution date
21 months
Budget
42 millons €
CHARACTERISTICS
Construction of singular building of Biomedicine Faculty of Valencia University. The building is constructed by a rectangular base below ground where three four floor identical towers stand. The base is formed by two floors of parking, one floor with complementary technical services and one main floor that develops an own internal enclosure, one open square, perimetrally surrounded by different rooms.<br>
The construction process that has been executed maximize the open excavation and minimize the excavation below the three underground slabs, and this excavation has been made in one single phase: from basement level 1 to background slab, making easy the movement of excavation machinery.