Bailén station of line 5 of Metro Valencia

Construction of metro station by construction of a tunnel during the regular railway service of the line. The enclosure has been made attached to the existing tunnel by slurry walls, the  dimensions in top view plant are 250 m long and 10 m wide. The works of infrastructure, track and catenary assembly, railway signage, architectural finishes of the station and service installations (ventilation, electricity MV and LV, plumbing, mechanical, access control) are included in this Project.
The main elementary works are the following:
– Reinforced concrete slurry walls: 8.200 m2
– Excavation protected by slurry walls: 42.000 m3
– Structural concrete: 15.400 m3
– Reinforced steel: 2.160.000 kg
– Structural steel: 112.000 kg

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn