Madinah Depot, Haramain High Speed Train. Saudi Arabia
Location
Medina (Arabia Saudí)
Contracting entity
RENFE-Saudi Railways Organization
Execution date
24 months
Budget
290 millons €
CHARACTERISTICS
The works consist of the execution of the workshops of the high-speed line between the holy cities of Medina and Meca in Saudi Arabia. These workshops make up a complex of 3 buildings of 9,765, 16,650 and 27,600 m2 of metal structure and a framework of 24 railway tracks, distributed over 4 rail yards. Implementation of different work systems such as transfer trolleys, wheel lathes, low boogies, pit drop, blowing systems, emptying, sandblasting, pit tracks, slab tracks, work pits and shuttle, as well as 29 offices within the buildings.
Earthworks of more than 170,000 m3
Assembly of more than 32 km of UIC60 tracks
42 switches including 1 crossing
60,000 m2 of sandwich panel and translucent cladding
4,650,000 kg of structural steel
1,200,000 kg of corrugated steel