Improvement of the East Quay. Phase 2

CHARACTERISTICS

The works consisted in the repair and improvement of the breakwater, parallel to shore ,over a length of more than 5 km.
The main actions corresponded with:
– Repair of breakwater slope and foot with rockfill.<br>
– Protection berms in slope foot with rocks and 10 ton concrete cubic blocks.
 -New slope protection over existing  one, formed by concrete blocks of 50 tons.
Supplies and placement riprap 4 tons.
Riprap material recovery from existing quaids: 48.353 Tn.
Supplies and placement riprap 500-1.000 kg:  3.456 Tn.
Concrete in blocks of 50 tons: 122.743 m³.
Concrete in blocks of 10 tons: 6.835 m³.
Transport and placement ,blocks of 50 tons: 5.713 uds.
Transport and placement, blocks of 10 tons: 1.608 uds.

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn