PPP Circuit 6 – Route 6 Cuchilla Grande section – Route 12

FEATURES

Public-Private Participation (PPP) project aimed at the design, construction and maintenance of 78km of road, with a total term of 20 years, the first three of which are intended for the construction and the remaining ones for the operation of the section, which will receive availability payments. from the Ministerio de Transportes y Obras Públicas.

The financing is supported by entities including BBVA, BROU and IDB.

For the first two years, widening and reinforcements will be carried out on the road sections with traffic, so that a phased construction procedure has been developed to avoid the need for traffic cuts and minimize road safety risks.

BSM (Bitumen Stabilized Material) technology, known as foamed bitumen, was used in the design for the reinforcement of the existing pavements. Existing pavement layers will be milled and recycled to produce BSM1 in plant and BSM2on-site.

During the second and third years, works will be undertaken on San Ramón By-Pass which will provide the town with a section of a new floodable route, as opposed to the current route.

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn