Superstructure and Architectural in burying works of line 1 of MetroValencia at Benimamet Station

CHARACTERISTICS
The work carried out are divided in three main blocks:<br>
Track Assembly and electrification. Track on ballast on surface track and fixed directly over concrete slab on underground track. RENFE truck catenary adapted to FGV.
Rail: 6.120 m
Elastomeric blanket:  5.800 m2
Track catenary: 3.700 m
Construction of 2 station: Benimámet and Les Carolines-Fira. Lobby for access to platforms, Tickets sale room and technical rooms.
Structural Steel: 171.000 kg
Aluminium enclosure: 4.600 m
Glazed 10+10 with reflective tempered butyral sheet: 3.000
Station installation (ventilation and mechanical, plumbing and sewerage, fire protection, signage to the traveller) and railway installation (signage, control and railway communication)

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn