REPLACEMENT OF TWO METAL BRIDGES IN SOLLEFTEÅ, SWEDEN

Characteristics

The contract consists of the disassembly and demolition of two metallic bridges from the 1920s and the construction of two new metallic bridges in the same location and using the same existing piers and abutments.

The Rörströmsälven bridge has three spans of 16+16+45 meters and the Fjällsjöälven bridge, has three spans of 38+55+38 meters.

Rover is in charge of both, the project and the execution of these bridges. The contract is highly complex, due to the short period of time to be able to carry out the work, given that there are only 5 months of track closure in which the existing bridges must be dismantled and the new ones assembled.

The new bridges are assembled on one of the sides of the rivers to later push them to the final location.

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn