Bulk Cargo Terminal Infrastructure, Phase I

CHARACTERISTICS

Dredging works in access channel and basin up to -20.00 m. depth. Slope protection with riprap and geotextile, land reclamation and ground improvements with stone columns. Jetty construction with reinforced concrete deck  slab of dimensions 400 x 35 m., founded over steel piles of diameter 1500 and 1000 mm. and 50 m. long, 30 m. embedded. Execution of 150,000 m2. in land surface.
– Removing preloads:  375.000 m3
– Dredging and fillings: 1.330.000 m3
– Soil improvement with stone columns: 173.000 m3
– Steel piles: 10.800 t.
– Concrete deck slab: 47.000 m3
– Steel reinforcement in deck slab: 4.830 t.
– Geotextiles and waterproofing in esplanades: 230.000 m2
– Base layers stabilized with cement: 110.000 m2
– Bituminous pavement : 25.430 m2
– Railroad track: 4.341 m

Careers

Work
with us

Be part of a leading, international team in infrastructure development, committed to the professional growth of its people. Join Rover and work in a safe, diverse, and inclusive environment where teamwork, communication, and a spirit of continuous improvement drive new challenges and collective success.

LinkedIn

Rover Grupo | LinkedIn Rover Grupo | 44.308 seguidores en LinkedIn. 60 años construyendo sueños | Bienvenido a Rover Grupo!! Empresa valenciana de desarrollo de infraestructuras con presencia internacional. La empresa cubre todos los ámbitos de la obra civil: carreteras y autovías, ferrocarriles, marítimos, conservación de aguas, urbanizaciones, hospitales, fotovoltaica...

Follow us on LinkedIn